Pre-possession inspection report

Sample: 2 BHK, Sohna Road, Gurugram

Flat
Tower C, 9th floor, 2 BHK
Inspected
Saturday, 10:00 to 14:30
Present
Owner, Gharkala site lead
Documents checked
Agreement for sale, builder’s specification sheet

Scope and limits

A visual, non-invasive inspection of the finishes, fittings and services inside the flat, with room measurements. It is not a structural certificate, a legal or title opinion, or a valuation. Measurements are for the owner’s discussion with the builder, not a licensed surveyor’s certificate.

Gharkala also designs and builds interiors. This report is prepared independently of that, the fee is adjustable against any interiors contract with us, and you are free to use this report with any contractor you choose.

Summary

3

Critical

Safety, water getting in, or electrical

7

Major

Fix before you accept handover

12

Minor

Finish and cosmetic

Measurements against your agreement

Measured wall to wall with a laser meter at skirting height. Carpet area follows the RERA definition: it includes the area under internal partition walls and excludes external walls, service shafts and the balcony.

RoomMeasured (ft)Area (sq ft)
Living and dining19′ 4″ × 11′ 2″215.9
Main bedroom13′ 0″ × 11′ 0″143.0
Second bedroom11′ 6″ × 10′ 4″118.8
Kitchen10′ 2″ × 7′ 6″76.3
Two bathrooms, passage, internal walls—143.5
Carpet area measured697.5
Carpet area in the agreement712.0
Difference−14.5 (−2.0%)

We report the measured number against the number in your agreement, with the method above. Whether a difference entitles you to a refund is a question for the builder and, if needed, your lawyer or RERA. We don’t give legal opinions.

Defect schedule (first 10 of 22)

Each number matches a tag we left on site, so the builder’s team can find every item without us.

#WhereWhat we foundSeverityPhoto
1Main bathroomFloor slopes away from the drain. Water from a flood test pooled near the door for 20 minutes.Criticalphoto
2KitchenSocket next to the sink has no earth (tester shows open earth).Criticalphoto
3Second bedroom, external wallDamp patch below the window sill, moisture reading about 3× the dry wall nearby. Likely gap in the window frame sealing.Criticalphoto
4Living room9 floor tiles sound hollow when tapped, near the balcony door. Marked in chalk.Majorphoto
5Main bedroomWardrobe-wall plaster bulges 6 mm over a 2 m straight edge.Majorphoto
6BalconyRailing gap 140 mm at one end, wider than the rest. Check against the spec.Majorphoto
7Second bathroomBasin mixer is a different brand from the specification sheet.Majorphoto
8Main doorDoor drags on the floor in the last 10 cm of its swing.Majorphoto
9Kitchen platformGranite joint not filled, 3 mm gap at the sink cut-out.Minorphoto
10Living roomPaint patches and roller marks on the ceiling near the light point.Minorphoto

The full report continues with the remaining items and a floor plan of your flat drawn to scale from our measurements.

What to do next

  1. Send this report to the builder’s customer care and ask their site engineer to sign the snag list.
  2. Agree a date for the fixes, in writing, before you sign the handover.
  3. Book a re-check once they say it’s done. We confirm each numbered item is fixed.
Book an inspection How the inspection works